Application Review Schedule for Nichols Ranch
The following table summarizes the key milestones in the schedule that the U.S. Nuclear Regulatory Commission (NRC) has established for its review of the application that Uranerz Energy submitted to obtain a license for its Nichols Ranch In Situ Recovery site.
Key Milestones | Completion Date Actual - A Target - T |
Application Tendered | 11/30/07 – A |
Acceptance Review |
Acceptance Review Start | 1/31/08 – A |
Docketing Decision Letter Issued/Acceptance Review Complete | 4/14/08 – A |
Safety Review * |
Requests for Additional Information (RAIs) Issued to Applicant | 9/11/08 – A |
Final Safety Evaluation Report (SER) completed | 7/19/11 – A |
Environmental Review |
RAIs Issued to Applicant | 3/12/09 – A |
Draft SEIS issued to EPA | 12/11/09 – A |
Public comment period | 3/3/10 – A |
Final SEIS issued to EPA | 1/21/11 – A |
License |
License issued | 7/19/11 – A |
* Timeline does not include extended lead times for applicants to respond to RAIs or open issues.
Information on Federal Register notices for receipt of the application and opportunity to request a hearing or petition to intervene can be found on the Hearing Opportunities page.

Page Last Reviewed/Updated Tuesday, March 09, 2021