Application Review Schedule for Reno Creek
The following table summarizes the key milestones in the schedule that the U.S. Nuclear Regulatory Commission (NRC) has established for its review of the application that AUC, LLC submitted to obtain a license for its Reno Creek In Situ Recovery site.
Key Milestones | Completion Date Actual - A Target - T |
Application Tendered | 10/05/12 |
Acceptance Review |
Acceptance Review Start | 03/18/13 - A |
Docketing Decision Issued/Acceptance Review Complete | 06/18/13 - A |
Safety Review * |
Requests for Additional Information (RAIs) Issued to Applicant | 02/10/14 - A |
Final Safety Evaluation Report (SER) completed | 09/30/16 - A |
Environmental Review * |
RAIs Issued | 02/10/14 - A |
Draft SEIS issued | 06/30/16 - A |
Public comment period ends | 09/06/16 - A |
Final SEIS issued | 12/16/16 - A |
License |
Licensing Action Completed - License, Record of Decision, and Final Revised SER Issued | 02/17/17 - A |
* Timeline does not include extended lead times for applicants to respond to RAIs or open issues.
Information on Federal Register notices for receipt of the application and opportunity to request a hearing or petition to intervene can be found on the Hearing Opportunities page.