Application Review Schedule for Reno Creek

The following table summarizes the key milestones in the schedule that the U.S. Nuclear Regulatory Commission (NRC) has established for its review of the application that AUC, LLC submitted to obtain a license for its Reno Creek In Situ Recovery site.

Key Milestones Completion Date
Actual - A
Target - T
Application Tendered 10/05/12
Acceptance Review
Acceptance Review Start
03/18/13 - A
Docketing Decision Issued/Acceptance Review Complete
06/18/13 - A
Safety Review *
Requests for Additional Information (RAIs) Issued to Applicant
02/10/14 - A
Final Safety Evaluation Report (SER) completed
09/30/16 - A
Environmental Review *
RAIs Issued
02/10/14 - A
Draft SEIS issued
06/30/16 - A
Public comment period ends
09/06/16 - A
Final SEIS issued
12/16/16 - A
License
Licensing Action Completed - License, Record of Decision, and Final Revised SER Issued
02/17/17 - A

* Timeline does not include extended lead times for applicants to respond to RAIs or open issues.

Information on Federal Register notices for receipt of the application and opportunity to request a hearing or petition to intervene can be found on the Hearing Opportunities page.

To top of page

Page Last Reviewed/Updated Tuesday, March 09, 2021