Application Review Schedule for Ross
The following table summarizes the key milestones in the schedule that the U.S. Nuclear Regulatory Commission (NRC) has established for its review of the application that Strata Energy, Inc. submitted to obtain a license for its Ross In Situ Recovery site.
Key Milestones | Completion Date Actual - A Target - T |
Application Tendered | 01/06/11 – A |
Acceptance Review |
Acceptance Review Start | 05/02/11 – A |
Docketing Decision Letter Issued/Acceptance Review Complete | 06/28/11 – A |
Safety Review |
Requests for Additional Information (RAIs) Issued to Applicant | 01/25/12 – A |
Safety Evaluation Report (SER) completed | 02/28/13 – A (Revised 2/4/14) |
Environmental Review |
RAIs Issued | 01/25/12 – A |
Draft SEIS issued | 03/2013 – A |
Public comment period ends | 05/13/13 – A |
Final SEIS issued | 02/28/14 –A |
License |
Licensing Action Completed - License Issued* | 04/24/14 – A |
* Based on signed Programmatic Agreement for the Consultations under Section 106 of the National Historic Preservation Act by April 22, 2014.
Information on Federal Register notices for receipt of the application and opportunity to request a hearing or petition to intervene can be found on the Hearing Opportunities page.