Application Review Schedule for Ross

The following table summarizes the key milestones in the schedule that the U.S. Nuclear Regulatory Commission (NRC) has established for its review of the application that Strata Energy, Inc. submitted to obtain a license for its Ross In Situ Recovery site.

Key Milestones Completion Date
Actual - A
Target - T
Application Tendered 01/06/11 – A
Acceptance Review
Acceptance Review Start
05/02/11 – A
Docketing Decision Letter Issued/Acceptance Review Complete
06/28/11 – A
Safety Review
Requests for Additional Information (RAIs) Issued to Applicant
01/25/12 – A
Safety Evaluation Report (SER) completed
02/28/13 – A
(Revised 2/4/14)
Environmental Review
RAIs Issued
01/25/12 – A
Draft SEIS issued
03/2013 – A
Public comment period ends
05/13/13 – A
Final SEIS issued
02/28/14 –A
License
Licensing Action Completed - License Issued*
04/24/14 – A

* Based on signed Programmatic Agreement for the Consultations under Section 106 of the National Historic Preservation Act by April 22, 2014.

Information on Federal Register notices for receipt of the application and opportunity to request a hearing or petition to intervene can be found on the Hearing Opportunities page.

To top of page

Page Last Reviewed/Updated Tuesday, March 09, 2021