Application Review Schedule for Willow Creek
The following table summarizes the key milestones in the schedule that the U.S. Nuclear Regulatory Commission (NRC) has established for its review of the application that Uranium One USA, Inc. submitted to renew its license for the Willow Creek in situ recovery facility.
Key Milestones | Completion Date Actual - A Target - T |
Application Tendered | 5/30/08 – A |
Acceptance Review |
Docketing Decision Letter Issued/Acceptance Review Complete | 12/24/08 – A |
Safety Review |
Requests for Additional Information (RAIs) Issued to Applicant | 3/24/09 – A |
Final Safety Evaluation Report (SER) completed | 10/2011 – T |
Environmental Review |
RAIs Issued to Applicant | 3/24/09 – A |
Draft EA issued | 5/25/10 – A |
Public comment period | 6/9/10 – A |
Final EA issued | 7/7/11 – A |
License |
Licensing Action Completed | 10/2011 – T |

Page Last Reviewed/Updated Tuesday, March 09, 2021