2009 NRC Documents for Fermi, Unit 3 Application

The following table provides access to documents and correspondence that the NRC has issued in 2009 in connection with its review of the COL application that Detroit Edison Company submitted for Fermi, Unit 3.

This page includes links to files in non-HTML format. See Plugins, Viewers, and Other Tools for more information.

Date Description
11/13/09 Environmental Project Manager Change for the Combined License Environmental Review for Fermi 3
11/06/09 Requests For Additional Information Letter No. 2 Related To The Environmental Review For The Combined License Application For Fermi Nuclear Power Plant, Unit 3
07/02/09 Environmental Scoping Summary Report
06/30/09 Fermi Nuclear Power Plant Unit 3 Combined License Application Review Schedule
06/29/09 Trip Report - June 9-11, 2009, Hydrology-related Site Visit In Support Of Fermi 3 Combined License Application
05/12/09 Requests for Additional Information Related to the Environmental Review for the Combined License Application for Fermi Nuclear Power Plant, Unit 3

Page Last Reviewed/Updated Monday, March 9, 2020