Part 21 Report - 1997-620
ACCESSION #: 9706190261
GPU Nuclear, Inc.
G P U One Upper Pond Road
NUCLEAR Parsippany, NJ 07054-1095
Tel 201-316-7000
June 12, 1997
6730-97-2176
U. S. Nuclear Regulatory Commission
Attention: Document Control Desk
Washington, DC 20555
Gentlemen:
Subject 10CFR Part 21 30-Day Report
Oyster Creek Nuclear Generating Station
Docket No. 50-219
Potential Failure of General Electric Type CR120AD Relays
Oyster Creek has experienced failures of the General Electric Type
CR120AD relays. The failure mechanism was identified as a manufacturing
defect; specifically, part of the start-end pigtail of the relay coils
was off the insulating lead pad and, therefore, lying directly on the
outer layer of the winding. This configuration placed insulation on the
affected length of magnet wire in a high-electrical-stress condition that
led to dielectric breakdown at the failure site, thus effectively short
circuiting the coil.
Although our evaluation of all ten potentially defective relays installed
at Oyster Creek concluded that their fail-safe mode does not impact plant
safety, this potential defect is being conservatively reported in
accordance with 10 CFR Part 21.21, (d) (3) (ii).
Should you have questions regarding this matter, please contact Yosh
Nagai of our staff at (201) 316-7974.
Sincerely,
T. G. Broughton
President
YN/plp
c: Administrator, Region I
NRC Resident Inspector
Oyster Creek NRC Project Manager
10 CFR 21 - 30 DAY WRITTEN REPORT
CONCERNING POTENTIAL FAILURE OF
GENERAL ELECTRIC TYPE CR120AD RELAYS
1. Name and Address Of The Individual Informing The Commission:
Name: T. G. Broughton
President
Address: GPU Nuclear, Inc.
One Upper Pond Road
Parsippany, NJ 07054-1149
II. Basic Component Affected:
General Electric Type CR120AD Relays
III. Firm Supplying Components:,
General Electric Nuclear Energy
175 Curtner Avenue
San Jose, California 95125
IV. Nature of the Potential Defect:
On March 26, 1996 Oyster Creek Generating Station issued a deviation
report which identified an open coil in three CR120AD relays
dedicated for safety-related use: one relay failed immediately after
the installation when energized, another relay failed within two
days during startup test and a third failed some months later during
a surveillance test. Following these incidents a coil from one of
the failed relays was sent to General Electric (GE) for analysis and
the two remaining relays were sent intact to an independent research
laboratory (Southwest Research Institute) for failure analysis.
After the analysis, Southwest Research Institute concluded that the
principal problem observed in both relay coils was a manufacturing
defect: specifically, part of the start-end pigtail of the coil was
off the insulating lead pad and, therefore, lying directly on the
outer layer of the winding, which was near the finish end of the
coil. This configuration placed insulation on the affected length
of magnet wire in a high-electrical-stress condition that led to
dielectric breakdown at the failure site, thus effectively short
circuiting the coil. Resulting high current through the short
circuit caused the magnet wire to fuse and produced an energetic arc
at the failure site.
There are ten (10) potentially defective relays installed at Oyster
Creek. GPU Nuclear has concluded that their fail-safe mode does not
Impact plant safety. However, there may be other nuclear facilities
with these relays installed or kept in their warehouse without
knowing of or about this potential failure.
V. Date on which Potential Defect Was Identified.
We determined on May 9, 1997 that this potential failure of the GE
relay CR120AD could have a generic implication and it was reported
to NRC Operations Center, by phone, on May 9, 1997.
VI. Number and Location of Components.
There are ten (10) potentially defective relays installed at Oyster
Creek.
VII. Corrective Actions Taken
If a premature failure of any of these relays occurs, with an "open"
coil as the failure mechanism, we may consider replacing the
remaining nine relays. However, replacement of the ten relays is
not scheduled at this time for the following reasons:
i) The previous failures of the CR120AD relays at Oyster Creek
occurred either immediately upon energization or within a few
months of operation. Also, none of the installed relays have
failed since their installation approximately seven months ago.
ii) The probability of these relays having a potential
manufacturing defect is extremely low.
iii) Our evaluation concluded that there is no impact to plant
safety due to their fail-safe mode feature.
GPU Nuclear, Inc.
G P U One Upper Pond Road
NUCLEAR Parsippany, NJ 07054-1095
Tel 201-316-7000
June 12, 1997
6730-97-2176
U. S. Nuclear Regulatory Commission
Attention: Document Control Desk
Washington, DC 20555
Gentlemen:
Subject: 10 CFR Part 21 30-Day Report
Oyster Creek Nuclear Generating Station
Docket No. 50-219
Potential Failure of General Electric Type CR120AD Relays
Oyster Creek has experienced failures of the General Electric Type
CR120AD relays. The failure mechanism was identified as a manufacturing
defect; specifically, part of the start-end pigtail of the relay coils
was off the insulating lead pad and, therefore, lying directly on the
outer layer of the winding. This configuration placed insulation on the
affected length of magnet wire in a high-electrical-stress condition that
led to dielectric breakdown at the failure site, thus effectively short
circuiting the coil.
Although our evaluation of all ten potentially defective relays installed
at Oyster Creek concluded that their fail-safe mode does not impact plant
safety, this potential defect is being conservatively reported in
accordance with 10 CFR Part 21.21, (d) (3) (ii).
Should you have questions regarding this matter, please contact Yosh
Nagai of our staff at (201) 316-7974.
Sincerely,
T. G. Broughton
President
YN/plp
c: Administrator, Region 1
NRC Resident Inspector
Oyster Creek NRC Project Manager
10 CFR 21 - 30 DAY WRITTEN REPORT
CONCERNING POTENTIAL FAILURE OF
GENERAL ELECTRIC TYPE CR120AD RELAYS
1. Name and Address Of The Individual Informing The Commission:
Name: T. G. Broughton
President
Address: GPU Nuclear, Inc.
One Upper Pond Road
Parsippany, NJ 07054-1149
II. Basic Component Affected:
General Electric Type CR120AD Relays
III. Firm Supplying Components:
General Electric Nuclear Energy
175 Curtner Avenue
San Jose, California 95125
IV. Nature of the Potential Defect:
On March 26, 1996 Oyster Creek Generating Station issued a deviation
report which identified an open coil in three CR120AD relays
dedicated for safety-related use: one relay failed immediately after
the installation when energized, another relay failed within two
days during startup test and a third failed some months later during
a surveillance test. Following these incidents a coil from one of
the failed relays was sent to General Electric (GE) for analysis and
the two remaining relays were sent intact to an independent research
laboratory (Southwest Research Institute) for failure analysis.
After the analysis, Southwest Research Institute concluded that the
principal problem observed in both relay coils was a manufacturing
defect: specifically, part of the start-end pigtail of the coil was
off the insulating lead pad and, therefore, lying directly on the
outer layer of the winding, which was near the finish end of the
coil. This configuration placed insulation on the affected length
of magnet wire in a high-electrical-stress condition that led to
dielectric breakdown at the failure site, thus effectively short
circuiting the coil. Resulting high current through the short
circuit caused the magnet wire to fuse and produced an energetic
arc at the failure site.
There are ten (10) potentially defective relays installed at Oyster
Creek. GPU Nuclear has concluded that their fail-safe mode does not
impact plant safety. However, there may be other nuclear facilities
with these relays installed or kept in their warehouse without
knowing of or about this potential failure.
V. Date on which Potential Defect Was Identified.
We determined on May 8, 1997 that this potential failure of the GE
relay CR120AD could have a generic implication and it was reported
to NRC Operations Center, by phone, on May 9, 1997.
VI. Number and Location of Components.
There are ten (10) potentially defective relays installed at Oyster
Creek.
VII. Corrective Actions Taken
If a premature failure of any of these relays occurs, with an "open"
coil as the failure mechanism, we may consider replacing the
remaining nine relays. However, replacement of the ten relays is
not scheduled at this time for the following reasons:
i) The previous failures of the CR120AD relays at Oyster Creek
occurred either immediately upon energization or within a few
months of operation. Also, none of the installed relays have
failed since their installation approximately seven months ago.
ii) The probability of these relays having a potential
manufacturing defect is extremely low.
iii) Our evaluation concluded that there is no impact to plant
safety due to their fail-safe mode feature.
*** END OF DOCUMENT ***
Page Last Reviewed/Updated Tuesday, March 09, 2021