Part 21 Report - 1997-731
ACCESSION #: 9804220183
COOPER NUCLEAR STATION
P.O. BOX 98, BROWNVILLE, NEBRASKA 68321
TELEPHONE (402)825-3811
FAX (402)825-5211
Nebraska Public Power District
NLS980069
April 16, 1998
U.S. Nuclear Regulatory Commission
Attention: Document Control Desk
Washington, D.C. 20555-0001
Gentlemen:
Subject: Follow-up to Interim Report Pursuant to 10 CFR 21.21
(a)(2) Cooper Nuclear Station, NRC Docket 50-298, DPR-46
Reference: 1. Letter NLS970124 to Document Control Desk (USNRC)
from P. D. Graham (NPPD) dated September 29, 1997,
"Interim Report Pursuant to 10 CFR 21.21 (a)(2),
Cooper Nuclear Station, NRC Docket 50-298, DPR-46"
2. Letter NLS970055 to Document Control Desk (USNRC)
from P. D. Graham (NPPD) dated March 27, 1997, "Reply
to a Notice of Violation, NRC Inspection Report No.
50-29 8/96-24, Cooper Nuclear Station, NRC Docket 50-
298, DPR-46"
3. Letter NLS970227 to Document Control Desk (USNRC)
from P. D. Graham (NPPD) dated December 26, 1997,
"Change of Commitment, Cooper Nuclear Station, NRC
Docket 50-298, DPR-46"
This letter provides closure to the interim 10 CFR Part 21 submitted to
the Commission on September 29, 1997 (Reference 1), and establishes a new
date for the completion of the Level 1 and 2 setpoint project committed
to in Reference 2.
In Reference 1, the Nebraska Public Power District (District) submitted
an interim report to the Commission pursuant to 10 CFR 21.21 (a)(2)
describing a condition where safety related setpoint calculations
provided to the District by General Electric Nuclear Energy (GENE) were
found to contain non-conservative errors. These non-conservatisms in the
Level 1 setpoint calculations (being done in support of the Improved
Technical Specifications project) were primarily a result of calculation
and math errors and had minimal impact on nuclear safety. Accordingly,
no substantial safety hazard could have been created (i.e., the condition
is not reportable pursuant to 10 CFR Part 21). Note that even if there
had been a potential significant impact, the affect would have been
limited to the proposed Improved Technical Specifications. There would
have been no impact on the current Technical Specifications and plant
operation.
Powerful Pride in Nebraska
NLS980069
Page 2 of 2
The Level 1 setpoint calculations for Improved Technical Specifications
have been reviewed and checked by an independent third party to assure
accuracy and correctness. However, the administrative processing and
reformatting necessary for formal approval has yet to be completed as
committed to in Reference 3. Final approval of these calculations will
be completed by May 31, 1998.
In addition to the Level 1 setpoint calculations being done in support of
Improved Technical Specifications, the District committed by letter dated
March 27, 1997 (Reference 2), to review and update all Level 2 setpoints,
and their associated calculations, by December 31, 1997. However, this
project could not be completed until the potential 10 CFR Part 21 issue
was resolved. The District informed the Commission of this commitment
change in Reference 3 and committed to providing a new completion date
for the Level 1 and 2 setpoint project as part of the closure to the
potential 10 CFR Part 21 issue (i.e., this letter). Accordingly, the
Level 1 setpoints, which are those supporting Improved Technical
Specifications, will be completed by May 31, 1998, (as discussed above)
with the remainder of the project to be completed (i.e., the Level 2
setpoints) by December 31, 1998. Since this project is, in effect, a
validation and reconstitution of the design basis supporting previously
reviewed and approved setpoints, this delay in the project completion has
no safety significance.
Should you have any questions concerning this matter, please contact me.
Sincerely,
J. H. Swailes
Vice President
of Nuclear Energy
/crm
cc: Regional Administrator
USNRC - Region IV
Senior Project Manager
USNRC - NRR Project Directorate IV-1
Senior Resident Inspector
USNRC
NPG Distribution
ATTACHMENT 3 LIST OF NRC COMMITMENTS
Correspondence No: NLS980069
The following table identifies those actions committed to by the District
in this document. Any other actions discussed in the submittal represent
intended or planned actions by the District. They are described to the
NRC for the NRC's information and are not regulatory commitments. Please
notify the NLS Manager at Cooper Nuclear Station of any questions
regarding this document or any associated regulatory commitments.
COMMITTED DATE
COMMITMENT OR OUTAGE
Complete the Level 1 setpoints supporting ITS. May 31, 1998
Complete the review and updating of the Level 2 December 31, 1998
setpoints.
PROCEDURE NUMBER 0.42 REVISION NUMBER 6 PAGE 9 OF 13
*** END OF DOCUMENT ***
Page Last Reviewed/Updated Tuesday, March 09, 2021