Part 21 Report - 1997-751

ACCESSION #: 9710160120 ABB October 13, 1997 LD-97-028 Document Control Desk U.S. Nuclear Regulatory Commission Washington, DC 20555 Subject: Report Pursuant to 10 CFR 21 Regarding Certain Models of Potter & Brumfield Relays Gentlemen: The purpose of this letter is to notify the Nuclear Regulatory Commission of a defect pursuant to 10 CFR 21, "Reporting of Defects and Noncompliance." The identified "defect" is contamination of lubricant which has led to the hardening of the lubricant in certain Potter & Brumfield Products Division NOR relay models 170-1 and 7032 such that the relays could fail to function, These relays are used in the Plant Protection System (i.e., Engineered Safety Features Actuation System and Reactor Protection System). Waterford Steam Electric Station (WSES) has informed ABB-CE of four failed Potter & Brumfield Type MDR rotary relays. Although not all of the failed relays were supplied by ABB-CE, they were manufactured by Potter & Brumfield at the same facility utilizing similar components, lubrication material, and techniques. The failed relays initially reported were limited to AC versions of the MDR Relay. A recently reported failure of a Model 7032 (DC Version) relay by WSES may indicate that the problem applies to both AC and DC voltage relays. Potter & Brumfield has verbally indicated that they believe model MDR relays potentially affected are date-coded 94XX, and that earlier (93XX) and later (95XX) date-coded relays are not affected. WSES had a failure analysis of each relay performed by Southwest Research Institute after removal of the relay from service, In all cases, Southwest Research Institute identified the problem to be hardened bearing lubricant. Potter & Brumfield's initial evaluation of the reported problem is that the lubricant hardening effect is likely due to contaminants introduced into the lubricant and potentially excessive application of lubricant which occurred during assembly of the suspect relays. ABB Combustion Engineering Nuclear Operations Combustion Engineering, PO. Box 500 Telephone (203) 638-1911 Inc. 1000 Prospect Hill Road Fax (203) 285-9512 Windsor, Connecticut 06095-0500 LD-97-028 Page 2 ABB-CE's investigation to date has revealed that Potter & Brumfield supplied approximately 96 relays of the models identified above to ABB-CE that are date-coded 94XX. These have been supplied to various nuclear power plants as delineated in the attachment as part of the information specifically required by 10 CFR 21. Very truly yours, COMBUSTION-ENGINEERING, Inc. Ian C. Richard, Director Operations Licensing cc: M. F Barnoski (ABB-CE) Attachment to LD-97-028 ABB Combustion Engineering Nuclear Operations 10 CFR 21 Report of a Defect or Failure to Comply The following information is provided pursuant to 10 CFR 21.21 (c)(4): (i) Name and address of the individual informing the Commission: Ian C. Rickard, Director Operations Licensing Combustion Engineering 2000 Day Hill Road Windsor, CT 06095-0500 (ii) Identification of the facility, the activity, or the basic component supplied for such facility or such activity within the United States which fails to comply or contains a defect: The basic components are Potter & Brumfield MDR relay models 170-1 and 7032. Information from Potter & Brumfield indicates that the concern potentially affects not only the 170-1 and 7032, but also the 7033 and 7034 relays date-coded 94XX (iii) Identification of the firm constructing the facility or supplying the basic component which fails to comply or contains a defect: The relays were supplied to ABB-CE by Potter & Brumfield and were subsequently provided to the nuclear plants identified in item (vi) below by: Combustion Engineering, Inc. 2000 Day Hill Road Windsor, CT 06095-0500 (iv) Nature of defect or failure to comply and the safety hazard which is created or could he created by such defect or failure to comply: The defect is lubricant contamination and excessive application of lubricant leading to hardening of the lubricant in Potter & Brumfield MDR relay models (date-coded 94XX) 170-land 7032 and potentially 7033 and 7034 such that the relays could fall to function. These relays are used in the Plant Protection System (i.e., Engineered Safety features Actuation System and Reactor Protection System), and their failure could prevent proper functioning of the Plant Protection System. 2 Attachment to LD-97-028 (v) The date on which the information of such defect or failure to comply was obtained. ABB-CE received information regarding failures of the subject relays on August 6, 1997. (vi) In the case of a basic component which contains a defect or fails to comply, the number and location of all such components in use at, supplied for, or being supplied for one or more facilities or activities subject to the regulations of this - part: ABB-CE has supplied MDR relays as replacement or original equipment as follows: Utility Plant Model Nos. Arizona Public PVNGS 1, 2, 3 7032,7033,7034 Service Co. Entergy ANO 2 7032,7033,7034.170-1 Entergy Waterford 3 7032,7033,7034,170-1 Edison SONGS 2, 3 7032,7033,7034,170.1 International, Inc. These relays are normally energized, and are deenergized to actuate. (vii) The corrective action which has been, is being, or will be taken; the name of the individual responsible for the action; and the length of time that has been or will be taken to complete the action: ABB-CE is currently evaluating potential corrective actions. (viii) Any advice related to the defect or failure to comply about the facility, activity, or basic component that has been, is being, or will be given to purchasers or licensee: In parallel with providing this 10 CFR 21 report to the NRC, ABB-CE will distribute copies of the report to utilities having an ABB-CE designed Nuclear Steam Supply System. Those utilities will also be provided with ABB-CE's recommended corrective actions, when developed. GENERAL INFORMATION or OTHER EVENT NUMBER: 33077 LICENSEE: ABB COMBUSTION ENGINEERING NOTIFICATION DATE: 10/13/97 CITY: WINDSOR REGION: 1 NOTIFICATION TIME: 13:42 [ET] COUNTY: STATE: CT EVENT DATE: 08/06/97 LICENSE#: AGREEMENT: N EVENT TIME: 00:00[EDT] DOCKET: LAST UPDATE DATE: 10/13/97 NOTIFICATIONS JOHN PELLET RDO NRC NOTIFIED BY: HESS VERN HODGE NRR HQ OPS OFFICER: CHAUNCEY GOULD EMERGENCY CLASS: NOT APPLICABLE 10 CFR SECTION: CCCC 21.21 UNSPECIFIED PARAGRAPH EVENT TEXT ABB COMBUSTION REPORTED A PART 21 ON CERTAIN MODELS OF POTTER & BRUMFIELD RELAYS. THEY HAVE IDENTIFIED THE "DEFECT" AS CONTAMINATION OF LUBRICANT WHICH HAS LEAD TO THE HARDENING OF THE LUBRICANT IN CERTAIN POTTER & BRUMFIELD PRODUCTS DIVISION MDR RELAYS(MODELS "170-1" AND "7032"). THIS "DEFECT" COULD RESULT IN RELAY FAILURE. THESE RELAYS ARE USED IN THE PLANT PROTECTION SYSTEM. THERE IS ALSO THE POTENTIAL FOR RELAY MODELS 11703311 AND 11703411 TO FAIL TO FUNCTION CORRECTLY. THESE RELAYS HAVE BEEN SUPPLIED TO PALO VERDE 1, 2 AND 3, ARKANSAS NUCLEAR ONE UNIT 2, WATERFORD 3, AND SAN ONOFRE 2 AND 3. ABB-CE IS CURRENTLY EVALUATING POTENTIAL CORRECTIVE ACTIONS WHICH WILL BE PROVIDED TO THE UTILITIES WITH ABB-CE DESIGNED NUCLEAR STEAM SUPPLY SYSTEMS. *** END OF DOCUMENT ***

Page Last Reviewed/Updated Tuesday, March 09, 2021