Part 21 Report - 1998-201
ACCESSION #: 9802110143
Illinois Power Company
Clinton Power Station
P.O. Box 678
Clinton, IL 61727
Tel 217 930-0023
Fax 217 935-4632
Walter G. MacFarland IV
Chief Nuclear Officer
ILLINOIS
POWER U-G02925
4F.140
An Illinova Company
February 6, 1998
Docket No. 40-561
Document Control Desk
Nuclear Regulatory Commission
Washington, D. C. 20555
Subject: 10CFR21 Report 21-97-058: ITT Barton Hydramotor
Pressure Reducing/Dump Valve Internal Leak
Dear Madam or Sir:
On December 10, 1997 Illinois Power (TP) initiated Condition Report
1-97-12-165 due to oil leaking around the diaphragm of a replacement
pressure reducing/dump valve installed on a ITT Barton Hydramotor
actuator. The pressure reducing/dump valve is part number NS108916A
supplied by ITT Barton. This was discovered prior to declaring the
Hydramotor operable during post maintenance testing of the Hydramotor to
determine if the associated damper met its required closing time.
Hydramotors are used at Clinton Power Station to operate safety-related
dampers in ventilation systems. Two additional pressure reducing/dump
valves were removed from the storeroom and bench tested. One of the two
additional valves removed from the storeroom had a leak similar to the
one that was installed on the Hydramotor in the plant, the other valve
successfully passed the bench test. Investigation into this condition
revealed that the observed problem with the pressure reducing/dump valve
could cause the Hydramotor to close the damper slower than the design
required time. This is contrary to the purchase specification for the
Hydramotor which specifies the required damper closing time. This issue
was identified as potentially reportable under the provisions of 10 CFR,
Part 21.
On the basis that the pressure reducing/dump valve does not meet the
requirements of the procurement document and that the identified
deficiency with the pressure reducing/dump valve could cause an isolation
damper for a safety related system to close slower than assumed in the
plant design, IP has concluded that this issue is reportable under the
provisions of 10 CFR, Part 21.
U-602925
Page 2
IP is providing the following information in accordance with
10CFR21.21(d)(4). Initial notification of this matter will be provided
by facsimile of this letter to the NRC Operations Center in accordance
with 10CFR21.21(d)(3) within two days of the date the responsible officer
signs this letter.
(i) Walter G. MacFarland IV, Senior Nuclear Officer of IP, Clinton
Power Station, Highway 54, 6 Miles East, Clinton, Illinois,
61727, is informing the Nuclear Regulatory Commission of a
condition reportable under the provisions of 10CFR, Part 21.
(ii) The basic component involved in this condition is a replacement
pressure reducing/dump valve, part number NS108916A, for ITT
Barton Hydramotors.
(iii) The pressure reducing/dump valve were supplied to Clinton Power
Station by ITT Barton, City of Industry, California.
(iv) The pressure reducing/dump valve had a leak in the diaphragm
area. The cause of the leak appears to be poor machining or
workmanship of the valve at the time of manufacture. In
certain applications Hydramotors are required to close dampers
in a specified time. With the identified deficiency in the
pressure reducing/dump valve the Hydramotor may close slower
than required to meet the time specified by the purchase
specification. For example, the failure of a Hydramotor in the
Standby Gas Treatment System to operate in the required time
could affect control room habitability in an accident
situation.
(v) The deficient pressure reducing/dump valve was identified and
determined potentially reportable under the provisions of
10CFR21 on December 10, 1997.
(vi) There are 103 applications where pressure reducing/dump valves
of this model are in service at Clinton Power Station. IP is
not aware of other facilities that could be affected by this
deficiency. Fifteen pressure reducing/dump valves are located
in the storeroom.
(vii) The fifteen spare pressure reducing/dump valves located in the
storeroom (this includes the two that failed) will be sent to a
vendor to determine if they operate properly. The vendor will
rework valves, if possible, that are determined not to operate
properly. When pressure reducing/dump valve are installed in a
Hydramotor that have a design required closing time, Clinton
Power Station procedures require that they are time tested to
ensure they meet the design requirements. The leak deficiency
would be identified during time testing. Therefore, no action
is being taken for currently installed valves.
(viii) IP has no advice about this issue for other purchasers or
licensees.
U-602925
Page 3
Additional information about this issue may be obtained by
contacting L. T. Chaney, Nuclear Station Engineering Department, at (217)
935-8881, extension 3658.
Sincerely yours,
Walter G. MacFarland, IV
Chief Nuclear Officer
MRS/krk
cc: NRC Clinton Licensing Project Manager
NRC Resident Office, V-690
Regional Administrator, Region III, USNRC
Illinois Department of Nuclear Safety
INPO Records Center
ASCO (ITT Barton)
*** END OF DOCUMENT ***
Page Last Reviewed/Updated Tuesday, March 09, 2021