Part 21 Report - 2000-190

Cutler-Hammer
Nuclear Programs
130 Commonwealth Drive, Warrendale, PA 15086

LTROO342
August 30, 2000

Document Control Desk
United States Nuclear Regulatory Commission
Washington. DC 20555

Attention: Director, Office of Inspection and Enforcement

Subject: Potential failure to close on demand for DS 206 Circuit Breaker

The following information is provided pursuant to the requirements of 10CFR Part 21 to report a potential safety concern. This issue concerns the possibility for malfunction of the Eaton Cutler-Hammer DS 206 circuit breakers due to "shock-out" of Direct Trip Actuators (DTA's). Shock-out is defined as the unwarranted or undesired change in the state of a DTA from the normally un-tripped state to a tripped state. Shock-out occurs as a result of shock caused by the circuit breaker cycling from the open position to the closed position. This shock force is supplied by the closing springs striking the bottom plate of the breaker frame during the breaker closing operation. The result of shock-out is that the DTA trips immediately. returning the breaker to an open condition, which is neither required nor desired.

Shock-out has been observed in DS 206 breakers after replacing the operating mechanism and/or closing springs during reconditioning. Shock-out has NOT been observed in new DS 206 breakers or in DS 206 breakers reconditioned in accordance with Eaton Cutler-Hammer Nuclear Programs (C-HNP) procedures. The standard C-HNP reconditioning process does not routinely replace Operating Mechanisms or Closing Springs. DTA's that exhibited shock-out in breakers reconditioned with new operating mechanisms and/or new closing springs did NOT exhibit shock-out when installed and extensively tested in a new DS 206 breaker.

C-HNP has supplied safety related operating mechanisms, closing springs and DTA's to a single nuclear customer. The non-nuclear, commercial segment of Eaton Cutler-Hammer has sold the same items to third party suppliers. Third party suppliers may have provided the same items to the nuclear Industry as safety related. After the C-HNP customer identified the problems with DTA shock-out, an investigation was conducted to determine the cause(s) of the problem. Some of the actions taken during the investigation included:

1) C-HNP insured that the customer was installing the DTA's In accordance with the guidance provided In the commercial instruction book for the breaker.

2). DTA's that appeared to be susceptible to shock-out in the customer's reconditioned DS 206 breakers were installed into current vintage new DS 206 breakers. The DTA's were tested with several different force closing springs. No shock-out was observed.

LTR00342
Page 2

3) Following high-speed videography of the breaker undergoing shock-out1 C-HNP performed a modified reconditioning of a customer breaker that had exhibited repeated shock-out. The customer specifically requested the C-HNP reconditioning process be modified to NOT include every standard OEM recommended upgrade. The reconditioning process did include the upgrade to the Trip Shaft Bearing Plate that is part of the current configuration of production DS 206 Circuit Breakers. Significant improvement in breaker performance was seen although shock-out still occurred when using the highest force Closing Springs available.

4) Design modifications to the existing DTA were prototyped, evaluated and tested. DTA magnetic coupling Increased by approximately 30% over the present DTA design. Testing in a shock-out prone breaker revealed that shock-out might still occur with the re-designed DTA.

5) Previous design changes made to both the Closing Springs and DTA's were examined and evaluated as to their possible effect. No design changes were Identified which would lead to a conclusion that they were a factor in the shock-out problem.

The result of the investigation undertaken by C-HNP reveals the following contributing causes.

1) DTA shock-out was experienced in DS 206 breakers that were reconditioned by the customer. The customer reconditioning process included the replacement of the breaker operating mechanism with a new mechanism and in some cases with new closing springs.

2) The vintage of the subject circuit breakers were such that the Levering In Device of the breakers being reconditioned were not equipped with a Reverse Override Pin which was a modification introduced in the mid 1970's.

3) The customers reconditioning process was not the same process recommended by Cutler-Hammer: the OEM.

4) The amount of force generated by the Closing Springs appears to relate to the susceptibility of these early vintage breakers to exhibit shock-out. The nominal design spring force for the closing spring for the DS 206 has not changed since 1967. Closing springs, with spring force near the upper tolerance limit, installed in a test breaker (older vintage customer reconditioned breaker with new operating mechanism) resulted in a higher frequency of shock-out. The same springs installed In a new breaker with a DTA that had shocked-out In the test breaker did NOT result in shock-out.

C-HNP has determined that the root cause of DTA shock-out in DS 206 breakers is the replacement of operating mechanisms and/or closing springs with new operating mechanisms and/or new closing springs, as part of the standard reconditioning process. DTA shock-out has not been observed in vintage DS 206 breakers that are reconditioned In accordance with C-HNP procedures, which does not include the replacement of operating mechanisms and/or closing springs as part of the standard reconditioning process. The standard C-HNP reconditioning process DOES Include installation of design upgrades.

LTR00342
Page 3

To eliminate the possibility of shock-out, when the DS 206 breaker reconditioning process includes installation of a new operating mechanism and/or closing springs, C-HNP recommends the installation of a modified bottom plate to eliminate transmission of shock to the DTA. A modified bottom plate has been designed, tested and is being seismically qualified by C-HNP.

This deficiency was identified and determined to be of a chronic reportable nature on approximately July 31, 2000.

The installed base of the C-HNP supplied operating mechanisms and closing springs is limited to a single utility and plant, Tennessee ValIey Authority Sequoyah Nuclear Plant. C-HNP does not know where operating mechanisms and closing springs, procured commercially by third party dedicators, may have been installed in safety related applications.

For additional information the Licensee should contact Eaton Cutter-Harnmer Nuclear Programs at (724) 779-5931

Sincerely,
Eaton Cutler-Hammer Programs

Laurence D. Patterson
Manager. Quality Assurance

General Information or Other Event Number: 37275
Rep Org: EATON CUTLER-HAMMER Notification Date / Time: 08/30/2000 15:06 (EDT)
Licensee: EATON CUTLER-HAMMER Event Date / Time: 07/31/2000 (EDT)
Last Modification: 08/30/2000
Region: 1 Docket #:
City: Warrendale Agreement State: No
County: License #:
State: PA
NRC Notified by: Laurence Patterson Notifications: Pete Eselgroth RI
HQ Ops Officer: Leigh Trocine Caudle Julian R2
Melvyn Leach R3
Chuck Paulk R4
Vern Hodge (fax) NRR
Emergency Class: N/A
10 CFR Section:
CCCC 21.21 UNSPECIFIED PARAGRAPH

EVENT TEXT

10 CFR PART 21 NOTIFICATION REGARDING THE POTENTIAL FAILURE OF EATON-CUTLER-HAMMER DS-206 CIRCUIT BREAKERS TO CLOSE ON DEMAND

The following text is a portion of a facsimile received from Eaton Cutler-Hammer Nuclear Programs personnel:

"The following information is provided pursuant to the requirements of 10 CFR Part 21 to report a potential safety concern. This issue concerns the possibility for malfunction of the Eaton Cutler-Hammer DS-206 circuit breakers due to 'shock-out' of Direct Trip Actuators (DTA). Shock-out is defined as the unwarranted or undesired change in the state of a DTA from the normally un-tripped state to a tripped state. Shock-out occurs as a result of shock caused by the circuit breaker cycling from the open position to the closed position. The shock force is supplied by the closing springs striking the bottom plate of the breaker frame during the breaker closing operation. The result of shock-out is that the DTA trips immediately, returning the breaker to an open condition, which is neither required nor desired."

"[Eaton Cutler-Hammer Nuclear Programs (C-HNP)] has determined that the root cause of DTA shock-out in DS-206 breakers is the replacement of operating mechanisms and/or closing springs with new operating mechanisms and/or new closing springs, as part of the standard reconditioning process. DTA shock-out has not been observed in vintage DS-206 breakers that are reconditioned in accordance with C-HNP procedures, which does not include the replacement of operating mechanisms and/or closing springs as part of the standard reconditioning process. The standard C-HNP reconditioning process DOES include installation of design upgrades."

"To eliminate the possibility of shock-out, when the DS-206 breaker reconditioning process includes installation of a new operating mechanism and/or closing springs, C-HNP recommends the installation of a modified bottom plate to eliminate transmission of shock to the DTA. A modified bottom plate has been designed, [and] tested and is being seismically qualified by C-HNP."

This deficiency was identified and determined to be of a chronic reportable nature on approximately July 31, 2000."

"The installed base of the C-HNP supplied operating mechanisms and closing springs is limited to a single utility and plant, Tennessee Valley Authority Sequoyah Nuclear Plant. C-HNP does not know where operating mechanisms and closing springs, procured commercially by third party dedicators, may have been installed in safety-related applications."

(Contact the NRC operations officer for supplier contact information.)