Date |
Subject |
04/25/2017 |
Mixed Oxide Fuel Fabrication Facility- Amended Response to Apparent Violations in NRC Inspection Report 70-3098/2016-005, EA-16-010
|
03/16/2017 |
CB&I AREVA MOX Services Reply to Notice of Violation 70-3098/2016-004-001 |
03/02/2017 |
Applicant Performance Review Of Authorized Construction Activities For CB&I AREVA MOX Services Mixed Oxide Fuel Fabrication Facility, Docket Number 70-3098 |
02/14/2017 |
U.S. Nuclear Regulatory Commission Evaluation Of Revision To The "Fundamental Nuclear Material Control Plan, Dated April 25, 2016, As Revised October 17, 2016" For The Mixed Oxide Fuel Fabrication Facility |
12/20/2016 |
Principal Structure System and Component 047 "Sintered Silicon Nitride Barrier" Completion Verification Report for Mixed Oxide Fuel Fabrication Facility Under Construction in Aiken, South Carolina |
11/29/2016 |
Assessment Follow-up Letter of Authorized Construction Activities for CB&I AREVA MOX Services Mixed Oxide Fuel Fabrication Facility |
11/21/2016 |
Letter to D. Gwyn from D. Tiktinsky re: MOX LA ISAS Update 2016 Approval |
10/21/2016 |
Closure of Generic Letter 2015-01, "Treatment of Natural Phenomena Hazards in Fuel Cycle Facilities" For the Mixed Oxide Fuel Fabrication Facility |
10/17/2016 |
CB&I AREVA MOX Services - Response to NRC RAI Regarding Revision of the Material Control and Accounting Plan |
10/06/2016 |
Request for Additional Information Related to the April 2016 Revision of the Fundamental Nuclear Material Control Plan for the Mixed Oxide Fuel Fabrication Facility, Under Construction in Aiken, South Carolina |
10/06/2016 |
Memo from DTiktinsky to RJohnson re: PSSC-29 Closure Sept 2016 |
08/08/2016 |
CMPP SER for April 2016 Revision
|
08/04/2016 |
CB&I AREVA MOX Services, LLC - Mixed Oxide Fuel Fabrication Facility PSSC-047 Completion Letter |
05/26/2016 |
CB&I AREVA MOX Services - Mixed Oxide Fuel Fabrication Facility - PSSC-029 Completion Letter |
01/29/2016 |
Response to PSSC Letter U.S. Nuclear Regulatory Commission Response to Mixed Oxide Services Request Related to the Development of a 10CFR 70.23 (a)(8)Completion Process. |
01/20/2016 |
CB&I AREVA MOX Services, LLC Submittal of Summary of Facility Changes During 2015 |
01/20/2016 |
CB&I AREVA MOX Services, LLC Submittal of 2016 Redacted License Application |
01/14/2016 |
U.S. Nuclear Regulatory Commission Acceptance of the Summary of Changes to the Application for the Mixed Oxide Fuel Fabrication Facility 2015 Update |
12/21/2015 |
CB&I AREVA MOX Services 10CFR70.23(a)(8) Completion Process |
12/17/2015 |
CB&I AREVA MOX Services Transmittal of Response to Request for Additional Information Regarding Revision of the Classified Matter Protection Plan, Dated January 29, 2015 |
12/02/2015 |
CB&I AREVA MOX Services, LLC Response to Request for Additional Information Regarding Revision of the Fundamental Nuclear Material Control Plan, Dated January 19, 2015 |
11/23/2015 |
MOX MCA Plan RAI |
09/22/2015 |
NRC Request for Additional Information Related to the Revision of the Mixed Oxide Fuel Fabrication Facility Classified Matter Protection Plan |
09/09/2015 |
CB&I AREVA MOX Services, Response to NRC Generic Letter 2015 01, "Treatment of Natural Phenomena Hazards in Fuel Cycle Facilities" |
04/23/2015 |
2014 End Of Cycle MOX Fuel Facility Fabrication CAT 1 APR Meeting Summary
|
03/12/2015 |
Applicant Performance Review of Authorized Construction Activities for CB&I AREVA MOX Services Mixed Oxide Fuel Fabrication Facility, Docket Number 70-3098 |
11/03/2014 |
NRC Acceptance of the Summary of Changes to the Application for the Mixed Oxide Fuel Fabrication Facility 2014 Update |
08/26/2014 |
Shaw AREVA MOX Services, Mixed Oxide Fuel Fabrication facility, Updated Interim Report Notification: Deformed Bar Anchors |
03/19/2014 |
Applicant Performance Review of Authorized Construction Activities for Shaw AREVA MOX Services, Mixed Oxide Fuel Fabrication Facility |
03/13/2014 |
U.S. Nuclear Regulatory Commission Review of Chicago Bridge and Iron Restructuring and Impact on the Need for an Indirect Transfer of Control of the Construction Authorization |
09/26/2013 |
Letter from Shaw AREVA MOX Services, External Hazards Analysis |
06/24/2013 |
Shaw AREVA MOX Services, Mixed Oxide Fuel Fabrication Facility, Notification of and Summary of Changes to Previously Submitted Plans |
06/12/2013 |
U.S. Nuclear Regulatory Commission Approval for Withholding Information from Public Disclosure for the Mixed Oxide Fuel Fabrication Facility |
03/28/2013 |
Shaw AREVA MOX Services, External hazards Analysis |
03/21/2013 |
Request for Time Extension for an Updated License Application and Integrated Safety Analysis Summary |
02/25/2013 |
Applicant Performance Review of Authorized Construction Activities for Shaw AREVA MOX Services, Mixed Oxide Fuel fabrication facility, Docket Number 70-3098 |
02/14/2013 |
Use of Non-Cited Violations for the Mixed Oxide Fuel fabrication facility |
02/07/2013 |
Shaw AREVA MOX Services LLC, Mixed Oxide Fuel Fabrication Facility- Planned Closing of Indirect Transfer of Control of Construction Authorization No. CAMOX-001 |
02/01/2013 |
Determination of the Adequacy of the Corrective Action Program of Shaw AREVA MOX Services for the Mixed Oxide Fuel Fabrication Facility |
01/31/2013 |
Safety Evaluation Report of MOX Services Request for Written Consent to indirect Transfer of License with SER attachment |
01/31/2013 |
Memo to C. Bradley re: SHAW AREVA MOX Services: Notice of Order Approving Indirect Transfer of Control for Construction Authorization |
01/16/2013 |
Shaw AREVA MOX Services, Mixed Oxide Fuel Fabrication facility, Supplemental information in Support of Request for Consent to Indirect Transfer of Construction Authorization No. CAMOX-001 |
12/20/2012 |
Shaw AREVA MOX Services , Mixed Oxide Fuel fabrication facility- Supplemental Information in Support of Request for Consent to Indirect Transfer of Control of Construction Authorization No. CAMOX-001 |
12/19/2012 |
Shaw AREVA MOX Services, Submittal of Extension Request to License Application (LA) and Integrated Safety Analysis Summary (ISAS) in January 2013 |
12/17/2012 |
U.S. Nuclear Regulatory Commission Findings on Shaw AREVA MOX Services Question Related to Governing MOX Project Quality Assurance Plan Criterion for Commercial Grade Dedication for the Mixed Oxide Fuel Fabrication Facility |
11/27/2012 |
Shaw AREVA MOX Services, External Hazards Analysis Update |
10/03/2012 |
Shaw AREVA MOX Services: Notice of Application for Approval on an Indirect License Transfer, and Opportunity to Request a Hearing and Provide Written Comments |
10/01/2012 |
Shaw AREVA MOX Services, Mixed Oxide Fuel Fabrication Facility, Supplemental Information in Support of Request for Consent to Indirect Transfer of Control of Construction Authorization No. CAMOX-001 |
08/30/2012 |
Request for Consent to Indirect Transfer of Control of Construction Authorization No. CAMOX-001 |
11/19/2010 |
Shaw AREVA MOX Services-Import Licensing Requirements in Support of Equipment for Use at the Mixed Oxide Fuel Fabrication Facility |
09/29/2010 |
Shaw AREVA MOX Services - Updates to the Physical Protection Plan and Training and Qualification Plan for the Mixed Oxide Fuel Fabrication Facility |
02/23/2010 |
In-Office Review Summaries: Mixed Oxide Fuel Fabrication Facility (Criticality Reviews 3 Through 8) |
07/09/2009 |
In-Office Review Summaries: Mixed Oxide Fuel Fabrication Facility (Chemical Safety) |
06/26/2009 |
In-Office Review Summary: Mixed Oxide Fuel Fabrication Facility (Human Factors) |
04/17/2009 |
In-Office Review Summaries: Mixed Oxide Fuel Fabrication Facility (Chemical Safety) |
03/16/2009 |
In-Office Review Summary: Mixed Oxide Fuel Fabrication Facility (Material Handling Equipment and Heavy Lift Cranes) |
02/06/2009 |
In-Office Review Summary: Mixed Oxide Fuel Fabrication Facility (Civil/Structural) |
12/16/2008 |
In-Office Review Summary: Mixed Oxide Fuel Fabrication Facility (Chemical Safety) |
11/13/2008 |
In-Office Review Summary: Mixed Oxide Fuel Fabrication Facility Management Measures |
11/13/2008 |
In-Office Review Summary: Mixed Oxide Fuel Fabrication Facility (Fire Safety) |
10/02/2008 |
In-Office Review Summary: Mixed Oxide Fuel Fabrication Facility (Red Oil Aspects of Chemical Safety) |
06/24/2008 |
Summary of the In-Office Review with Shaw AREVA MOX Services on Physical Protection for the Mixed Oxide Fuel Fabrication Facility to be Built Near Aiken, South Carolina |
06/24/2008 |
In-Office Review Summary: Mixed Oxide Fuel Fabrication Facility (Fire Safety). |
06/20/2008 |
Summary of In-Office Review with Shaw AREVA MOX Services on Material and Accounting for the MIXED Oxide Fuel Fabrication Facility to be Built Near Aiken, South Carolina |
06/04/2008 |
In-office Review Summary with Shaw Areva MOX Services on the Classified Matter Protection Plan for the Mixed Oxide Fuel Fabrication Facility to be built near Aiken, South Carolina |
05/06/2008 |
U.S NRC Approval for Withholding Information for Public Disclosure for the Mixed Oxide Fuel Fabrication Facility |
05/02/2008 |
On-Site Review Summary: Mixed Oxide Fuel Fabrication Facility (Chemical Safety review Related to Alternate Feedstock) |
04/24/2008 |
In-Office Review Summary: Mixed Oxide Fuel Fabrication Facility, Chemical Safety Process |
04/04/2008 |
Docket Number 70-03098 Shaw AREVA MOX Services, LLC Mixed Oxide Fuel Fabrication Facility (MFFF) Notification under Provisions of 10 CFR 21.21 |
03/20/2008 |
Request for an Exemption from 10 CFR Part 21.3 "Commercial Grade Item" |
03/18/2008 |
In-Office Review Summary: Mixed Oxide Fuel Fabrication Facility, Chemical Process Safety Related to Red Oil Event Prevention |
03/18/2008 |
In-Office Review Summary: Mixed Oxide Fuel Fabrication Facility Human Factors Engineering |
03/05/2008 |
In-Office Review Summary: Mixed Oxide Fuel Fabrication Facility (Confinement and Fire Protection) |
01/24/2008 |
In-Office Review Summary: Mixed Oxide Fuel Fabrication Facility (Chemical Safety Review) |
01/14/2008 |
In-Office Review Summary: Mixed Oxide Fuel Fabrication Facility (Criticality Review I and II) |
12/20/2007 |
In-Office Review Summary: Mixed Oxide Fuel Fabrication Facility (Chemical Safety Review) |
11/29/2007 |
10/04/2007 Summary of Closed Technical Meeting with Shaw AREVA MOX Services on Material Control and Accounting for the Mixed Oxide Fuel Fabrication Facility to be Built Near Aiken, South Carolina |
11/15/2007 |
In-Office Review Summary: Mixed Oxide Fuel Fabrication Facility (Integrated Safety Analyses) |
10/02/2007 |
In-Office Review Summary: Mixed Oxide Fuel Fabrication Facility (Confinement Systems II) |
09/24/2007 |
In-Office Review Summary: Mixed Oxide Fuel Fabrication Facility (Civil/Structural Review II) |
09/24/2007 |
In-Office Review Summary: Mixed Oxide Fuel Fabrication Facility (Fire Protection II) |
08/14/2007 |
On-Site Review Summary: Mixed Oxide Fuel Fabrication Facility (Mechanical Systems Review)
|
08/13/2007 |
In-Office Review Summary: Mixed Oxide Fuel Fabrication Facility (Fire Safety Review) |
08/09/2007 |
In-Office Review Summary: Mixed Oxide Fuel Fabrication Facility (Confinement Systems Review) |
06/15/2007 |
05/17/2007 Summary of the Kickoff Meeting with SHAW AREVA MOX Services on the Chemical Safety Review of the License Application and Integrated Safety Assessment Summary for the Mixed Oxide Fuel Fabrication Facility to be Built Near Aiken, SC |
06/01/2007 |
04/19/2007 Summary of the Kickoff Meeting with Shaw AREVA MOX Services on the Plant Systems Review of the License Application and Integrated Safety Assessment Summary for the Mixed Oxide Fuel Fabrication Facility to be built near Aiken, SC |
04/11/2007 |
Summary of Kickoff meeting for the Physical Protection review of the MOX facility |
10/26/2006 |
Summary of Closed Meeting with MOX Services to Discuss the ISA Summary for the MFFF, October 26, 2006 |
09/27/2006 |
Summary Of Meeting With Duke Cogema Stone & Webster To Discuss The License Application And Integrated Safety Analysis Summary For The Mixed Oxide Fuel Fabrication Facility To Be Built Near Aiken, SC |
05/17/2006 |
Summary of In-House Review of Duke, Cogema, Stone and Webster Held in Charlotte, NC |
03/22/2006 |
Summary of In-House Review of Duke, Cogema, Stone and Webster Held in Charlotte, NC |
09/07/2005 |
Duke Cogema Stone & Webster Meeting Summary |