Perry Nuclear Power Plant Unit 1 – License Renewal Application

Aerial view of Perry Nuclear Power Plant Unit 1

On this page:

Application Information:

This page includes links to files in non-HTML format. See Plugins, Viewers, and Other Tools for more information.

To top of page

License Renewal Review Schedule

These schedules reflect work plans that are subject to change. Early completion of a milestone may affect the target date of future milestones. Subsequent meetings and comment periods may change based on the revised schedule. This work plan will be updated on a periodic basis. Please see the NRC Public Meetings Page or contact the below listed PM for the latest information on meetings and status.

Milestones Schedule Date Actual Date
Receive License Renewal Application (LRA) 07/2023 07/03/2023
Publish Federal Register Notice (FRN) – LRA Availability 08/2023 08/09/2023
Publish FRN – Docketing Acceptance/Rejection and Opportunity for Hearing 09/2023 09/29/2023
Publish FRN – Notice of Intent to Prepare an Environmental Impact Statement and Conduct Scoping 09/2023 10/10/2023
Public Meeting – Overview of Subsequent License Renewal Process and Environmental Scoping 10/2023 10/19/2023
Environmental Scoping Period Ends 10/2023 11/09/2023
Deadline for Filing Hearing Requests and Petitions for Intervention 11/2023 11/28/2023
Issue Draft Supplemental Environmental Impact Statement (SEIS) 08/2024  
Public Meeting – Draft SEIS Meeting, If Needed 09/2024  
End of DSEIS Comment Period 10/2024  
Issue Safety Evaluation Report (SER) 12/2024  
ACRS Subcommittee Meeting 02/2025  
Issue Final SEIS 04/2025  
U.S. Environmental Protection Agency FRN Published – Availability of Final SEIS 05/2025  
ACRS Full Committee Meeting 05/2025  
Decision – Director, NRR 08/2025  

To top of page

Public Involvement

The public is encouraged to participate in the reactor license renewal process through public meetings, and public comment periods on rules, renewal guidance, and other documents. The Reactor License Renewal Public Involvement page provides general information to help the public participate.

Date Description
10/19/2023

Meeting to conduct a scoping process to gather information necessary to prepare an environmental impact statement to evaluate the environmental impacts for the potential license renewal of the operating license for Perry Nuclear Power Plant, Unit 1.

Meeting Feedback

To top of page

Project Managers for Perry Unit 1

Perry Unit 1 PMs
License Renewal (Safety) Vaughn Thomas
License Renewal (Environmental) Lance Rakovan
Lead Power Plant Scott Wall

To top of page

Section Navigation

Page Last Reviewed/Updated Friday, October 13, 2023